The Swedish Maritime Administration (Sjöfartsverket) has selected a joint venture of Boskalis Sweden, Van Oord Sweden, and Rohde Nielsen for work to deepen and widen the fairway to the Port of Gothenburg under the Skandia Gateway project.
The base assignment is worth approximately SEK2.3 billion (US$230 million). Additional work is available through agreed options.
Sjöfartsverket, the Gothenburg Port Authority, and the joint venture plan to sign the contract at the end of 2026, provided the award decision is not subject to legal challenge.
The contract covers dredging of approximately seven million cubic metres of loose material and rock, together with adjustments to fairway markings. Work is scheduled to start in August 2027, and the entire project is expected to be completed in the autumn of 2028.
On completion, maximum vessel draught will increase from 13.5 metres to 16.5 metres. The port may also order additional work, allowing vessels with draughts of up to 17.5 metres.
The port already receives very large oceangoing vessels; however, the current fairway and harbour basin depths prevent the largest ships from calling fully laden.
Skandia Gateway is designed to serve container vessels measuring as much as 430 metres in length and 65 metres in beam. That is 30 metres longer and five metres wider than the vessels calling at the container terminal in October.
"Cargo volumes in the port are increasing, vessels are operating at greater draft, and the long-term congestion in other major European ports means that the fairway deepening continues to be of the utmost strategic importance," said Elin Dörrheide, the port's project manager for Skandia Gateway.
An earlier joint dredging procurement was cancelled in October 2025 after bids exceeded the budget for the state-funded part of the project. The procurement was then divided into separate packages.
A redesign in May 2026 narrowed selected fairway sections and reduced the dredging area while retaining the 16.5-metre draught and the 17.5-metre option.
NCC completed reinforcement of the westernmost 700 metres of the container terminal's south quay in October.
On October 13, Boskalis Sweden began blasting and dredging the first 50 metres of water alongside the quay. That work falls under a separate SEK202 million (US$20 million) contract awarded in April and is due for completion in March 2027.