Russia's Baltic Shipyard has completed structural assembly of the hull of Leningrad, the sixth Project 22220 nuclear-powered icebreaker.
The bow and stern stems have been fitted, as has an ice belt of high-strength steel up to 45 millimetres (1.8 inches) thick. Hull painting, equipment installation and work on the propeller and rudder systems are continuing at the St Petersburg yard, which is part of United Shipbuilding Corporation (USC).
Rosatom Director General Alexei Likhachev said on October 30 that the launch was planned for December 3, the Day of the Nuclear Icebreaker Fleet.
Leningrad was laid down on January 26, 2024, and both of its RITM-200 reactors were installed aboard in August. After launch, the icebreaker will undergo outfitting afloat, followed by mooring trials that will include start-up of the nuclear power plant.
Builder's sea trials will cover the power plant, electric propulsion, steering, speed and manoeuvrability. The acceptance act will be signed with the operator, Atomflot, after sea trials.
The February 2023 contract calls for delivery in December 2028. USC Director General Andrei Puchkov cited the same date in November 2025.
Sister ship Yakutia was launched in November 2022 and raised its flag in December 2024. Its handover to Atomflot was recorded in March 2025. It completed its full test cycle in March 2025 and sailed on its first operational voyage in April 2025.
The commissioning deadline for Chukotka, launched in November 2024, was moved to 2027. Baltic Shipyard announced on November 23 that steam-turbine testing had begun during mooring trials, following the earlier start-up of both reactors.