The US Congressional Budget Office (CBO) has estimated that building the US Navy's 15 proposed Trump-class nuclear-powered, guided-missile battleships would total about US$275 billion, excluding research and development.
The figure, in constant 2026 dollars, appears in the CBO's review of the navy's FY2027 shipbuilding plan, which was published on Thursday, November 19.
The estimate is unchanged from August and averages US$18.3 billion per ship.
The CBO estimated US$23.4 billion for the lead Trump-class ship and about U$18 billion each for the remaining 14.
The navy's earlier estimates of US$15.1 billion for the lead ship and an average of US$9.7 billion for follow-on ships did not include nuclear propulsion, which the navy selected late in planning.
The CBO said the navy had not yet revised those estimates.
The FY2027 plan replaces the 28 DDG(X) destroyers listed in the FY2025 plan with 15 battleships. It also calls for 57 Flight III Arleigh Burke-class destroyers, which the CBO estimated would average US$3.2 billion each.
The navy has requested US$1 billion for advance procurement in FY2027 and scheduled the first battleship purchase for FY2028, followed by purchases in FY2030 and FY2031.
Newport News Shipbuilding (NNS) in Virginia, the sole US yard certified to construct nuclear-powered surface ships, would handle final assembly. Other yards could fabricate sections and modules.
"The navy's new nuclear-powered battleship program could pose a particular challenge to the Newport News shipyard, which is slated to perform the battleships' final assembly," the CBO said.
In August, it warned that adding the work, "could lengthen the delays for those programs, in addition to delaying the construction of the battleship itself," referring to the yard's aircraft carrier and submarine construction programmes.
The navy has already moved delivery of the Gerald R. Ford-class carrier USS Enterprise from July 2030 to March 2031 and of sister ship USS Doris Miller from February 2032 to February 2034.
"CVN-81's construction schedule has been affected by the cascading impact of CVN-80 delays on shipyard footprint capacity," NNS spokesperson Todd Corillo told USNI News in May.
The navy's plan proposes US$7.2 billion over FY2027–2031 to improve productivity at its nuclear shipbuilders. It does not identify a final assembly slot at NNS for the lead battleship.
NNS parent company Huntington Ingalls Industries already distributes structural fabrication for submarines and carriers to other yards.
The Trump-class was announced in December 2025, with USS Defiant as the intended name of the lead ship.