The Panama Canal Authority's (ACP) Executive Manager and Locks Project Management Division and Contracting Officer, Jorge de la Guardia, has issued the Notice to Commence Work slated for August 25, 2009.
The scope of work includes a contract for the design and construction of the canal's new set of locks and water-saving basins on both the Pacific and Atlantic ends of the Canal.
"A new partnership with Grupo Unidos por el Canal (GUPC) has begun," said Mr de la Guardia.
GUPC, composed of Sacyr Vallehermoso, Impregilo, Jan De Nul and Constructora Urbana, together with its surety, Zurich American Insurance Company, submitted a US$400 million performance bond and a US$50 million payment bond on August 11.
"Today's issuance of the Notice to Commence is one of the most significant moments for the ACP since we broke ground on expansion in September 2007," said Panama Canal Administrator/CEO Alberto Alemán Zubieta.
The new set of locks contracting process began August 28, 2007, when the ACP released its request for qualifications for the project. The ACP announced four prequalified consortia, comprised of 30 companies from 13 countries, and released its request for proposals December 21, 2007.
From January 2008 through January 2009, the ACP held more than 50 meetings with the prequalified consortia and hosted field visits to the sites where the new set of locks will be built.
On March 3, three of the four prequalified consortia submitted bids for the contract during a public ceremony. The sealed price proposals, including the ACP's sealed owner's price, were signed by the notary public, the ACP contracting officer and the canal's inspector general and subsequently locked in a vault in Panama's National Bank.
The technical proposals were delivered to the Technical Evaluation Board to be assessed and scored. Upon completion of the technical evaluations, the ACP revealed the technical scores and opened the consortia's sealed price proposals in a public forum July 8.
The ACP calculated a final weighted score and showed on a large screen that GUPC garnered the highest total points. After ensuring GUPC's price proposal and contractor's qualifications complied with the established ACP requirements, the ACP awarded the consortium with the new set of locks contract July 15.
All of the consortia were notified of the results and given five days to review all of the documentation regarding the evaluations, as well as the proposals of the other consortia.
Following the five-day review, the ACP gave the consortia three days to file a protest. The ACP did not receive any protests from the competing consortia.
Expansion will build a new lane of traffic along the Panama Canal through the construction of a new set of locks, which will double tonnage capacity and allow the transit of much longer, wider ships.