Norled takes delivery of hybrid-electric ferry ahead of 2027 route takeover

The hybrid-electric ferry heads to Sandnessjøen for trials and safety verification, then a temporary charter, before Norled takes over the Stokkvågen–Træna service on February 1, 2027.
Søholmen
SøholmenNorled
Published on: 

Norwegian ferry operator Norled took delivery of the ferry Søholmen on Friday, November 20.

The vessel is the first of four new ferries for the Stokkvågen–Træna and Stokkvågen–Lovund services in Nordland county. Norled will begin operating both routes under a 10-year contract with Nordland County Municipality from February 1, 2027.

In Sandnessjøen, Norled will conduct fjord trials with Søholmen, test the ferry's berthing at the quays and complete International Safety Management (ISM) verification.

The company plans to charter the ferry out temporarily once the tests and safety verification are complete. Søholmen will then join the Stokkvågen–Træna fleet when Norled takes over the route in February.

According to project manager Eivind Solvang, the aim is to complete them and phase them in safely before the service starts. Søholmen, Risvær and Kvitvær will be the main vessels on the routes, while Sjona will serve as the reserve ferry.

Each ferry has a length overall of 84.5 metres, a beam of 15 metres, space for 60 cars and eight MWh of battery capacity. The three main vessels can carry 250 people including crew.

The main ferries will run primarily on electricity, with shore charging at the quays in Stokkvågen, Lovund and Træna. Diesel generators will provide backup if power or charging is unavailable.

Norled previously took delivery of Hella, the first of three battery-powered double-ended ferries for the Hella–Vangsnes–Dragsvik service in Vestland.