FEATURE | Curacao's 138-year-old Queen Emma Bridge undergoes electric refit and modernisation

A drive pontoon with two electric thrusters has replaced 1987-vintage diesel propulsion on Willemstad's floating swing bridge after an eight-week closure of St Anna Bay's pedestrian crossing.
Queen Emma Bridge swinging into position
Queen Emma Bridge swinging into positionHolland Shipyards Group
Published on: 

Curaçao's Queen Emma Bridge has returned to service in Willemstad with a fully electric drive pontoon built by the Holland Shipyards Group (HSG).

The new pontoon has replaced a diesel propulsion arrangement that had been in use since 1987, and the bridge was out of service from August 2 until late September.

The floating pedestrian crossing opened in 1888. It links the Punda and Otrobanda districts across St Anna Bay.

Its wooden walkway rests on 16 pontoons. The powered pontoon at the moving end swings the structure laterally about a pivot on the Otrobanda side, which clears the bay for vessels entering and leaving the harbour. The bridge lies within Willemstad's UNESCO-listed historic inner city and harbour.

Custom pontoon solution boasting improved serviceability and suitability in tropical environments

Queen Emma Bridge
Queen Emma BridgeCuraçao Ports Authority

"For more than 130 years, this bridge has been part of the identity of Willemstad,” HSG said on completion. “The challenge was therefore clear: modernise the technology, while preserving the icon.”

Maritime consultancy Ferry Easy began investigating electrification for Curaçao Ports Authority (CPA) in 2019 and worked closely with Royal Van der Leun on the studies. CPA then selected HSG through an international tender.

The contract covered the supply and installation of a new motor pontoon, a control cabin, and associated electrical systems. The shipbuilder said the design prioritised reliability under tropical conditions, maintenance accessibility, and long-term serviceability.

The pontoon was launched at the group's Werkendam yard on June 22. Co Kieboom, Operations Manager for Holland Shipyards Dredging, said the unit was fitted with two electric thrusters. He added that tests and trials with Van der Leun and Hydromaster would take place that week before ocean shipment.

Modular construction ensuring ease of integration into existing bridge arrangement

The new pontoon and control cabin
The new pontoon and control cabinHolland Shipyards Dredging/Co Kieboom

The cargo ship IJzerborg delivered the pontoon, together with the new control cabin, to Curaçao in late July. The pontoon was discharged into the water from the ship and moved to CPA's workshop to be prepared for installation.

On August 2, the bridge was disconnected and towed to the same workshop. CPA Public Relations Manager Sau Bridgewater-Chong told Curaçao.nu that August and September had been chosen as a relatively quiet period for cruise traffic.

The initial schedule paired daytime ferries with overnight buses. On August 7, CPA announced round-the-clock ferry service between the two districts.

Crews exposed the under-deck infrastructure to run new cabling, then attached the new pontoon to the existing bridge and connected its systems. CPA announced on September 8 that the pontoon had been positioned, its propellers fitted and the control cabin unveiled.

Maintenance was also carried out on some existing pontoons and on sections of the timber deck, structural beams, and the Otrobanda pivot.

Royal Van der Leun handled electrical engineering and installation, along with shore power, system integration, commissioning and testing.

"The electrical scope includes the installation of a new main distribution board on shore, as well as new and adapted cabling for the propulsion, control systems, lighting and other technical installations," the company said.

Approximately four kilometres of new cabling was laid along the bridge, and the CCTV camera and lighting systems were renewed. The renewed electrical system also powers the pedestrian gates, and street and navigation lights were upgraded to LED.

In normal operation, the drive draws power from the grid. A new transformer and power cables were installed by Aqualectra at Otrobanda to supply the drive. A diesel standby generator is available to supply power the electric drive if the grid supply fails.

Other structural upgrades to extend service life

The pontoon and cabin following installation
The pontoon and cabin following installationHolland Shipyards Group

CPA's objectives included cutting fuel consumption and direct exhaust emissions during swings and the risk of fuel and oil leaks from the old equipment.

CPA reported on September 21 that the bridge was back in St Anna Bay for testing and commissioning. The following day, Curaçao.nu reported that the new systems had been tested through opening and closing cycles and that the drive was running with very little motor noise.

The bridge itself last underwent a major renovation in 2005–2006. The upper layer of its timber deck was renewed in 2015, and in 2021, CPA partially removed the bridge to replace the main beam at the Punda end.

The former motor pontoon has gone to a workshop for reconditioning. It is due to return to service in place of one of the bridge's two fixed pontoons.

The modernised Queen Emma Bridge with LED navigation and street lights
The modernised Queen Emma Bridge with LED navigation and street lightsHolland Shipyards Group