Reclamation completed for northern berths of Singapore's Tuas Port phase two

With reclamation complete for the 23-metre-deep northern berths, PSA Singapore can proceed with terminal construction. Reclamation continues on the southern berths of the 21-berth phase.

Alan Bosworth

A joint venture of Penta-Ocean Construction, Hyundai Engineering and Construction and Boskalis has completed reclamation for the 23-metre-deep northern berths of phase two of Singapore's Tuas Port.

PSA Singapore can now proceed with terminal construction on the northern section of phase two, also known as finger three. Reclamation continues on the southern berths.

The Maritime and Port Authority of Singapore (MPA) has sequenced the marine works so that reclaimed areas can be handed over in stages. The first phase two handover took place in March 2026 and covered the areas for berths B7 and B8. The northern works involved building seawalls, reclaiming land, improving the ground and installing caissons.

The consortium won the phase two contract in 2018, and reclamation began that March. Phase two covers 387 hectares of reclaimed land bounded by a 9.1-kilometre seawall of 227 caissons. Boskalis's scope includes deepening the port basin and access channel and supplying reclamation sand.

PSA broke ground on phase two on November 20. The phase will have 21 berths at a water depth of 23 metres and 8.6 kilometres of wharf. Operations will commence progressively from 2028.

When all four phases are complete in the 2040s, Tuas will have 66 berths and an annual capacity of 65 million TEU.