APM Terminals Maasvlakte II in the Port of Rotterdam, Netherlands APM Terminals
Ports & Terminals

Rotterdam plans 711-metre quay extension at Maasvlakte II

The expansion would add an estimated 1.4 million TEU of annual handling capacity. The port authority expects its shareholders to make an investment decision in February 2027.

Alan Bosworth

APM Terminals and the Port of Rotterdam Authority outlined plans on November 24 to extend the quay at Prinses Amaliahaven by 711 metres.

The partners estimate that the 25-hectare expansion of the Maasvlakte II container terminal would add 1.4 million twenty-foot equivalent units (TEU) of annual handling capacity.

The new quay would serve deepsea ships, feeders, and inland vessels, though the partners have not specified how much quay each vessel class would use or how berth windows would be assigned.

The port authority expects its shareholders to make an investment decision in February 2027. Construction is scheduled to run from October 2027 to January 2030, with no date yet announced for the first commercial calls.

The port authority would build the quay wall, extend the landside crane rail by 428 metres, and dredge about 1.3 million cubic metres of sand. APM Terminals would develop terminal operations.

An initial section of the wider expansion has entered service, and the partners expect the existing terminal to remain fully operational during the works. The terminal currently has 500 metres of dedicated barge berthing and three barge cranes. Barges with stable volumes and punctual arrivals qualify for fixed weekly berth windows.