Reconstruction of five fishing port berths completed on Russia's Sakhalin Island

Berths on Sakhalin will handle up to 600,000 tonnes of fish products a year once grid connection work finishes before year-end, while dredging of the fishing port's approach channel continues to 2029.

Jens Karsten

Russian contractor Mostostroy-11 has completed the reconstruction of five berths at the fishing port within Korsakov Port on Sakhalin Island, with electricity connection work scheduled to finish before the end of 2026.

The works were carried out for Natsrybresurs as part of a project to create a logistics technopark at the port. Once commissioned, the berths will be able to handle up to 600,000 tonnes of fish products annually.

"All construction and installation work on the berth infrastructure has been completed, including asphalt surfacing and concreting,” said Maxim Zhogolev, Sakhalin Oblast's minister of transport and road infrastructure. ”Work is now under way to connect the facility to the electricity supply; we plan to complete it by the end of 2026,"

The Russian Federal Agency for Fishery has put the reconstructed berth length at 793 metres and total funding at RUB6.668 billion (US$81 million) under the federal targeted investment programme for 2024–2026. The construction contract was signed on July 22, 2024.

The facilities will serve fishing fleet vessels. An investor is also building a fish processing plant near the berths, according to the regional ministry.

Korsakov lies on Aniva Bay in southern Sakhalin, and navigation at the port operates year-round. Its fishing port facilities are located in the Middle Basin.