Offshore contractor Allseas has launched Echo, the first of two new offshore construction vessels (OCV) being built at Wuchang Shipbuilding Industry Group in Wuhan, China.
After months of hull assembly and outfitting, the yard used its side-launch platform to transfer the vessel into the water. Allseas said the operation took around four hours, including a pause for watertight integrity checks, before the vessel was fully afloat.
Echo will stay at the shipyard, with most of her remaining commissioning work to be carried out beside the quay.
Before delivery, her systems and equipment will be commissioned and tested in stages and prepared for operation. Sister vessel Pulse remains under construction at the same yard.
Allseas signed contracts for the pair in April 2025, with deliveries originally scheduled for September and December 2026. The company now schedules the first delivery for the fourth quarter of 2026 and the second for the first quarter of 2027.
The vessels will undertake subsea construction and intervention, decommissioning, remotely operated vehicle (ROV) support, and inspection, maintenance and repair work.
Both vessels are based on a Salt Ship Design design. Each will have a length of 100 metres, a breadth of 23 metres and DP2 dynamic positioning.
Equipment will include a 150-tonne active heave-compensated offshore crane, a hangar for two work-class ROVs rated to 4,000 metres, and a 1,500-kWh battery energy storage system. The propulsion design is methanol-ready.