Koverhar Harbour in Hanko, Finland Port of Hanko
Dredging

Contract awarded to deepen fairway in Hanko, Finland

State works on the Lappohja fairway are due to finish in early spring 2027. The deeper approach will not open to shipping until the Port of Hanko builds a new quay and dredges alongside it.

Alan Bosworth

The Finnish Transport Infrastructure Agency has contracted Wasa Dredging to deepen the state-owned section of the Lappohja fairway serving Koverhar Harbour in Hanko, Finland.

The contract was signed on Wednesday, November 18, and covers dredging to accommodate an increase in the fairway's design draught from 12 metres to 14 metres.

Work is due to begin in November, and the agency expects work on the state-owned section to be completed in early spring 2027. The agency estimates that deepening the section will cost €2.5 million.

The scope includes dredging about 30,000 cubic metres of material, removing about 10,000 cubic metres of underwater rock and modifying navigational aids. Reusable material will be stored at Koverhar for later port construction.

Work will continue around the clock using a dredging platform, barges, tugs and support craft. The agency has asked passing vessels to slow down near the works and keep at least 150 metres clear of the equipment. Temporary buoyage may narrow the available channel during construction.

The fairway will remain at its current 12-metre design draught until the Port of Hanko builds a new quay and dredges both its own fairway section and the water alongside to accommodate the 14-metre draught.

The port has obtained an environmental permit for the berth. Permit records describe it as a deepwater quay about 283 metres long.

Koverhar's existing berths, KOV 1 and KOV 2, have listed depths of 11 metres and nine metres respectively.

The Port of Hanko and Euroports plan to develop Koverhar into an offshore wind logistics hub for the Baltic Sea. When the letter of intent was announced in 2025, OX2 said the Noatun North project, backed by OX2 and Ålandsbanken Offshore Wind I, was expected to begin using the harbour in 2030.