Jan De Nul joint venture wins 15-year maintenance dredging contract in Bahia Blanca, Argentina

A separate deepening of the access channel to handle fully laden Suezmax crude tankers remains subject to a board decision that could take up to four years.

Jens Karsten

The Consorcio de Gestión del Puerto de Bahía Blanca in Argentina has awarded a 15-year maintenance dredging contract to a joint venture of Jan De Nul and Compañía Sudamericana de Dragados.

The tender also covers deepening of the main access channel and requires both works to go to the same bidder. However, execution of the deepening depends on a later decision by the authority's board.

The maintenance contract will run for 180 months from the awarding of the contract. Trailing suction hopper dredgers will maintain existing design depths in the main access channel from kilometre four to kilometre 97, as well as the access channel to Puerto Belgrano Naval Base.

Berths, manoeuvring areas and accesses at Ingeniero White, Galván and Puerto Rosales will be maintained through water-injection dredging over 30 campaigns, normally two per year. The authority may extend the programme by 12 months.

Under Article 40 of the tender, the board has up to four years from notification of the award to rule on the deepening. Its decision will take into account financing, projected traffic, and the timing of the investment.

If no resolution is issued within that period, the deepening is treated as rejected.

The deepening aims to allow outbound vessels with an operational draught of up to 15.7 metres.

The channel would be dredged from kilometre 22, opposite the oil terminal pier, to the natural 15.5-metre contour, provisionally at kilometre 103. It would have a bottom width of 190 metres.

The tender sets a ceiling price of US$97 million.

If the board approves the work, the contractor will have 90 days to begin dredging and 12 months to complete it.

Maintenance of the deepened channel would then run for 15 years from acceptance of the first deepened section.

The deepening was proposed so that Suezmax tankers can load full cargoes of Vaca Muerta crude at Puerto Rosales. Suezmax tankers currently depart the port reportedly at about 80 per cent of capacity.